Timelines 2016
| task | who | private | date | |
|---|---|---|---|---|
| Announcement of Important dates of Call for Academic Papers/Workshops/General Presentations | ||||
| Website able to accept proposals/Academic Track, Workshop, General Track | 21.01.2016 | |||
| Send Call for Papers/Presentations/Workshops | 21.01.2016 | |||
| Close Call for Workshops | ||||
| Early bird sponsorship deadline | ||||
| Decide and broadcast workshop selection | ||||
| Workshop Schedule Release | ||||
| Early Bird Registration Opens | ||||
| Academic abstract submission deadline | ||||
| Regular Track presentation deadline | ||||
| Begin community voting on presentations | 28.03.2016 | |||
| Academic Track Review Decisions | ||||
| Close community comments on presentations | ||||
| Preliminary program decisions made & posted | ||||
| Early Bird Registration Discount Ends | ||||
| Exhibitor Manuals distributed to all sponsors | ||||
| Code Sprint Basecamp | 21.08.2016 12:00 | |||
| Code Sprint/Workshops | 22.08.2016 | |||
| Code Sprint/Workshops | 23.08.2016 | |||
| B2B Meeting | 23.08.2016 ~ 11am-16pm | |||
| FOSS4G/Icebreaker | 24.08.2016 | |||
| FOSS4G/Bootsfahrt | 25.08.2016 | |||
| FOSS4G | 26.08.2016 | |||
| Code Sprint | 27.08.2016 | |||
| Code Sprint | 28.08.2016 bis 12 Uhr |